October 10, 2008

The decision is quite interesting as the case involved work on a plant in Turkey, for which, among other things a bank guarantee had been issued. The parties fell out, attempts were made at calling the guarantee and an ICC arbitration ensued. The Arbitral Tribunal (Dr. Daniel Busse, Dr. Gert Thoenen and Dr. Philipp Habegger as chairman) issued a partial award on April 9, 2008.

Case information

Docket number: 
4A_224/2008
Original language: 
German
Published: 
27 ASA Bull 290 (2009)
Parties
Appellant: 
Respondent: 
Counsel
Appellant: 
PDF version of the translation: 
Chairman: 
Arbitrator (s): 
February 5, 2014

The case involved a Turkish company and a Belgian company and the performance of some work on a compressor station in Turkey. A contract was signed in 2007, governed by Turkish law but with an ICC arbitration clause, with the venue in Geneva.

 

As a dispute arose for the payment of the services performed, an arbitration was initiated in November 2011 and Anne-Carole Cremades was appointed as sole arbitrator by the ICC.

 

Case information

Docket number: 
4A_446/2013
Original language: 
French
Published: 
32 ASA Bull 367 (2014)
Parties
Appellant: 
Respondent: 
Counsel
PDF version of the translation: