December 16, 2020

A._________ subcontracted the maritime portion of the construction of a sea terminal to B._________. In the course of the build, A.________ called in bank guarantees, split between USD and local currency (referred to in the anonymized decision as XXX). This forced B.________ to refinance. B.________ then initiated arbitration proceedings under the contract’s arbitration clause on several grounds.