Swiss Arbitration Decisions

Use double-quotes to match a sentence or a date. Format dates as follows: "month dd, yyyy". (eg.: "february 23, 2007")
Found 2 result(s)
June 18, 2020

A.________ is a producer of manganese ore and concluded a contract with C.________ to market and sell said ore. A dispute arose when the parties were not able to come to an agreement regarding the price at which of one of the deliveries should be sold to the end consumer.

Case information

Docket number: 
4A_93/2020
Original language: 
German
Parties
Appellant: 
Respondent: 
Counsel
PDF version of the translation: 
November 13, 2020

In 2009, the Bangladeshi government opened up permits to privately-operated power plants. In 2010, the competent authorities concluded a contract with E.E.________, one of the Respondents here, for the supply of power. E.E.________, in turn, concluded several supply contracts with the other Respondents and some additional companies. The Supply Contracts contained an arbitration clause.

 

Case information

Docket number: 
4A_124/2020
Original language: 
German
Parties
Counsel
PDF version of the translation: